Projects Under Construction

NTPC has formulated a long term Corporate Plan to become a 130 GW company upto 2032. In line with the Corporate Plan, the capacity addition under implementation presently:

No. PROJECT STATE MW
NTPC
1. Tapovan Vishnugud-Hydro Uttarakhand 520
2. Lata Tapovan-Hydro Uttarakhand 171
3. Rammam-Hydro West Bengal 120
4. TTPP-III Odisha 1320
5. Lara-II Chhattisgarh 1600
6. Singrauli-III Uttar Pradesh 1600
7. Darlipali-II Odisha 800
8. Sipat-III Chhattisgarh 800
9. Telangana Stage II Telangana 2400
10. New Nabi Nagar, Stage-II Bihar 2400
11. Gadarwara Stage II Madhya Pradesh 1600
Total 13,331
JV & Sub. Companies
1. Patratu Jharkhand 2400
2. Khurja-THDC Uttar Pradesh 660
3. Tehri PSP-THDC Uttarakhand 750
4. Pipalkoti-THDC Uttarakhand 444
Total 4,254
Grand Total (NTPC + JV & Sub. Companies) 17,585

 

Projects Under Planning

No. PROJECT STATE MW
NTPC
1. Lara- III Chhattisgarh 1600
2. TTPP- IV Odisha 800
3. Barauni- III  Bihar 800
Total 3,200
JV & Sub. Companies
1. Meja-II Uttar Pradesh 2400
2. Patratu Stage II Jharkhand 1600
3. Bhillai Exp. Chhattisgarh 800
4. BRBCL - II Bihar  800
5. Jhabua Exp. Madhya Pradesh 800
6. Obra D TPP Uttar Pradesh 1600
7. Anpara E Uttar Pradesh 1600
8. Khurja STPP -II Uttar Pradesh 800
9. Chhabra Exp. Rajasthan 1600
Total 12,000
Grand Total (NTPC + JV & Sub. Companies) 15,200